LOGISTICS REPORT
- The breakdown of the 93 CRP personnel is:
- Support Staff-13
- Drillers-10
- Scientists and Science Technicians - 58
- Distinguished Visitors - 12
K001:CAPE ROBERTS PROJECT (CRP2)
Antarctica New Zealand 1998/1999
Event Personnel:
RIDGEN Jeremy | NZ | Mechanic/Engineer | ||
HOWAT Brian | NZ | Engineer/Plant Operator | ||
SINCLAIR Peter | NZ | Carpenter | ||
PYNE Alex | NZ | Science Support Manager | ||
REID Brian | NZ | Electrician | ||
KNOX Murray | NZ | Plant Operator | ||
CONAGLEN Kevin | NZ | Carpenter/Field Assistant | ||
CLARKE Colleen | NZ | Paramedic/Camp Manager | ||
COWIE Jim | NZ | Project Manager | ||
ALEXANDER John | NZ | CRP Liaison Officer | ||
SKINNER Dennis | NZ | Chef | ||
VARCOE Kath | NZ | Camp Assistant | ||
BRICE David | NZ | Field Assistant | ||
BROWN Steve | NZ | Carpenter | ||
COOPER Pat | NZ | Drill Manager | ||
HOLLOWAY Leon | USA (NZ) | DV/Drill Engineer | ||
TANSEY Frank | NZ | Driller | ||
MACDONALD Malcolm | NZ | Driller | ||
MARCUSSEN John | NZ | Assistant Driller | ||
AVEY Michael | NZ | Assisstant Driller | ||
WOODFORD Sam | NZ | Assisstant Driller | ||
SYMONS Todd | NZ | Assisstant Driller | ||
KINGAN Tony | NZ | Assisstant Driller | ||
COLLIE Chris | NZ | Assisstant Driller | ||
EATON David | NZ | Assisstant Driller | ||
ANDERSON Joanna (Jo) | NZ | Science Technician* | ||
BRYCE Sonya | Australia | Science Technician* | ||
JACKSON Nick | NZ | Science Technician* | ||
BUTLER Edward | NZ | Science Technician* | ||
PLANKELL Eric | USA | Science Technician* | ||
WILSON Terry | USA | Scientist* | ||
RAFAT Nodi | USA | (Germ) Science Technician* | ||
PAULSEN Timothy | USA | Scientist* | ||
NEISSEN Frank | Germany | Scientist* | ||
KOPSCH Conrad | Germany | Science Technician* | ||
POLOZEK Kerstin | Germany | Science Technician* | ||
BARRETT Peter | NZ | Chief Scientist* | ||
WEBB Peter | USA | Science Leader, Crary Lab | ||
POWELL Ross | USA | Scientist* | ||
WOOLFE Ken | Australia | Scientist*page 2 | ||
ATKINS Cliff | NZ | Science Technician** | ||
EHRMANN Werner | Germany | Scientist** | ||
NAISH Tim | NZ | Scientist | ||
JANACEK Tom | USA | Core Curator | ||
CURRAN Matt | USA | Core Curator | ||
SCHERER Reed | USA | Scientist | ||
BOHATY Stephen | USA | Scientist | ||
DEVINE Rusty | USA | Scientist | ||
TABECKI Mike | UK | Science Technician | ||
KRISSEK Larry | USA | Scientist | ||
FIELDING Chris | Australia | Scientist | ||
LAVELLE Mark | UK | Scientist* | ||
STRONG Percy | NZ | Scientist | ||
PASSCHIER Sandra | USA | Scientist | ||
HANNAH Mike | NZ | Scientist | ||
WILSON Graeme | NZ | Scientist | ||
ASKIN Rosie | USA | Scientist | ||
SIMES John | NZ | Science Technician | ||
MCLEOD Barbara | USA | Science Technician | ||
WATKINS David | USA | Scientist | ||
VILLA Giuliana | Italy | Scientist | ||
TAVIANI Marco | Italy | Scientist | ||
SMELLIE John | UK | Scientist | ||
TALARICO Franco | Italy | Scientist | ||
AGHIB Fulvia | Italy | Scientist | ||
WONIK Thomas | Germany | Scientist** | ||
BUECKER Christian | Germany | Scientist** | ||
BRINK Jason | USA | Scientist* | ||
SCHOLZ Erich | USA | Science Technician** | ||
WILSON Gary | USA | Scientist | ||
SAGNOTTI Leo | Italy | Scientist | ||
FLORINDO Fabio | Italy | Scientist | ||
CLAPS Michele | Italy | Scientist** | ||
SANDRONI Sonia | Italy | Science Technician | ||
ALBERTI Mauro | Italy | Science Technician | ||
KETTLER Richard | USA | Scientist | ||
ARMIENTI Pietro | Italy | Scientist | ||
MAGGS Tom | Australia | DV/Enviro. Auditor AADiv | ||
FOX Jeff | USA (NZ) | CRP Distinguished Visitor (DV) | ||
CARTER Bob | Australia | CRP Distinguished Visitor | ||
GROBE Hannes Ger. | (USA) | DV/AWI Core Curator | ||
RAINE Ian | NZ | Scientist | ||
VEROSUB Ken | USA | Scientist | ||
HENRYS Stuart | NZ | Scientist | ||
VAN DER MEER Jaap | NZ | (N/lands) Scientist | ||
CITA Maria Bianca | Italy | ISC Member | ||
DAVEY Fred | NZ | Scientist/ISC Member | ||
TESSENSOHN Fra | NZ | Germany | ISC Member | |
HUCH Monika | Germany | CRP DV/Science Journalist | ||
ANDERSON Ian | Australia | CRP DV/Science Journalist | ||
FUETTERER Dieter | Germany | CRP DV/OMG Member | ||
THOMSON Michael | UK | Scientist/ISC Member | ||
ROBERTS Andy | UK (NZ) | Scientist |
CAPE ROBERTS PROJECT - CRP2 LOGISTICS REPORT 1998-1999
INTRODUCTION
1.1. 1998/1999 summer season was the second drill season for Cape Roberts Project and throughout this report will be referred to as CRP2 to distinguish it from the previous season: CRP1 1997/98.
1.2. CRP1 was terminated prematurely when a storm in late October broke up the sea ice near the Drill Site and threatened the safety of personnel and equipment. The drill site was located 15.25 kilometres east of Cape Roberts, over a water depth of 150 metres. A drill depth of 147.7 metres below sea floor (m bsf) was reached with a core recovery rate of 86%.
1.3. CRP1 exposed a number of inadequacies in the drilling system, the most serious involving the sea riser. Some parts of the sea riser (that part of the drill system suspended in the water) had design and manufacturing defects. Questions were also raised about the ability of the sea riser to withstand the strong currents in the drill site area. Another problem was the difficulty of embedding the sea riser in the sea floor. In the off-season significant and costly modifications were made to the sea riser.
AIMS OF CRP2
- To recover up to 700 meters of high quality rock core from a second drill hole east off Cape Roberts. The core from CRP2 would 'pick up' from where CRP1 core 'left off (ie. optimally with an overlap of up to 30m) to maintain an unbroken time sequence in the core.
- To conduct drill and logistics operations in an efficient, timely and safe manner.
- To conduct all operations in accordance with the Comprehensive Environmental Evaluation report and thereby minimise impact on the environment.
- To successfully recover enough core to justify a third drill season.
PLANNING
3.1.CRP2 could not have proceeded had the sea riser not been upgraded. Planning for this had begun even before CRP1 had finished as time was short and additional funding had to be approved by the Project partners. The view of the Operations Management Group (OMG) was that CRP2 was the last chance to both prove the drill technology and achieve the operational goal of obtaining a reasonable amount of core. If neither of these goals were achieved then the Project would be terminated.
a. | Ship Resupply January 1998. The main items of resupply were two 'new' CRP containers (plus rigid sledges) fitted out as extensions to the Rig's mud hut system and the Drill Site Laboratory. All went according to plan. |
b. | Post-Season Review. An International Steering Committee (ISC) meeting was held in Washington in early February 1998 at which sea riser options were discussed. It was agreed the best option was to refurbish the existing riser because of the limited time and funding available. A major study was then undertaken by a US company to determine the existing sea riser's capabilities. From the results of that study modifications followed. |
c. | Sea ice Monitoring. The first DMSP (infared) images were received from ASA by Science Support Manager (CRPSSM) and Cape Roberts Project Manager (CRPM)in early April 1998 and continued regularly from then. Dr Robert Onstott at ERIM also contributed regular interpretive reports on his website. CRPSSM predicted at the end of his April-May sea ice report that a 20 km strip of fast ice about 1 m thick had formed offshore of Cape Roberts. Although it was too early to make longer term predictions, ice formation had begun well. This proved to be the case, and the fast ice along the western coast remained stable for the remainder of the 1998 winter. Sea ice growth was also monitored at the American's ice runway and west of Arrival Heights, and these measurements confirmed what was found when the reconnaissance team travelled to Cape Roberts and then out to the Drill Site in early September. |
d. | USAP Assistance. At the annual Post Season-Pre Season planning meeting held in Denver by the US Program CRP requested US support for hauling the two 'new' containers from Scott Base to Marble Point. Three hundred helicopter hours were requested for the Project, to be equally shared between Antarctica New Zealand and USAP. The Project would also draw upwards of 30,000 litres of JP5 from Marble Point at a time or times to be arranged. All the above arrangements went according to plan. |
e. | Staff Recruitment. In early March 1998 CRPM initiated the CRP2 recruitment round with an 'expression-of-interest' letter and an employment questionnaire to all CRP1 employees. Most of the CRP1 support and drill staff wished to return for CRP2 and information obtained from the questionnaire responses proved useful in revising the contract. On the drill team, one driller from the previous season was not offered reemployment and one other was unavailable, necessitating two new drillers for CRP2. One member of the support team was not offered re-employment and one was unavailable. In addition to the two replacements, a new position was created - Camp Assistant - to take some of the workload off the Project Manager and Camp Manager. The Carpenter's length of employment was reduced to cover the period from September to mid-October. At the end of the drilling phase the Scott Base carpenter was seconded to Cape Roberts to help with the Drill Site and Camp decommissioning. This worked well. Movements Controller, Antarctica New Zealand (Ant NZ) was kept advised of all recruitment information such as addresses, individual contracts, salaries, travel arrangements, medical certificates, clothing forms and the like. |
f. | Integration of CRP Scientists into Pre-Season Planning. CRPM was advised of CRP2 scientists and their dates for flying to Antarctica in early June 1998. Minor changes were advised by the Chief Scientist as he was made aware of them. Movements Controller, Ant NZ was kept advised. The Movements section of Ant NZ was kept advised of all clothing and freight requirements of CRP2 scientists as advised to CRPM. The manifesting of scientists and their cargo went well from Ant NZ's point of page 3 view. There were, however, some misunderstandings again with the Italian science contingent who were the responsibility of the US Program. |
CRP2 CARGO
4.1. Winfly 98 Cargo. A total of nearly 31,700 lbs (14,400kg) of cargo was air freighted at Winfly 98 for the Project. Cargo consisted mainly of drilling equipment (sea riser rigid flotation modules −15,000 lbs - and additional steelwork), food - fresh, no-freeze and short shelf-life items, and science cargo.
4.2. Mainbody 98 Cargo. A total of 16,300 lbs (7,400kg) of cargo was air freighted during the season for CRP2. Of this, 6,000lbs (2,700kg) was for specialist drill 'muds'. Another 7,000 lbs (3,200kg) was science cargo, the majority for the two German science teams.
4.3. Resupply Items. Nearly 70 orders were raised during the drilling phase for resupply items that individually would have numbered well over a thousand. In terms of prompt delivery, most were important and about a quarter were 'urgent', ie. to replace a used, defective, near-defective or broken part. Fortunately most arrived on time. Timely delivery of over 2.5 tonnes of drill muds was appreciated. Resupply of 'freshies' needs to be looked at - weather delays couldn't be blamed for all the delays.
CRP2 PERSONNEL
a. | Scientists and Science Technicians - 53. |
b. | Support Staff - 13, which included the Project Manager and the Project Liaison Officer (CRPLO). |
c. | Drillers - 10, made up of a Drill Manager, two Drillers and seven Assistant Drillers |
d. | Science Support Staff - five, made up of the Science Support Manager and four Core Technicians. |
e. | CRP3 Official Visitors and Media - 12, made up of three from Australia, one from Britain, four from Germany, one from Italy and three from NZ/USA |
f. | Maintenance/Clean-up Team January 2000 - four, made up of CRPM, Electrician, Engineer/mechanic and Engineer/Asst Plant Operator. |
5.2. The 'permanent' population at Cape Roberts during drill operations (ie. October and November) was 35, made up of support staff (10), drillers (10), science support staff (5) and scientists (10). The Chief Scientist spent approximately a third of his time at Scott Base/McMurdo.
5.3. The Winfly team of nine was made up of CRPM, CRPSSM, Engineer, Mechanic, Plant Operator, Electrician, Paramedic/Camp Manager, Field Assistant/Carpenter, and Carpenter. CRPM remained at Scott Base until Mainbody, while the remaining eight people traversed to Cape Roberts in two Hagglunds all-terrain vehicles and began setting up the main camp and then the Drill Site camp.
page 45.4. Personnel Deployment. CRP2 personnel deployment to Antarctica was full of disruption. Winfly flights suffered extensive delays and turnarounds. Four flights were scheduled from 20 to 26 August. The first successful flight was on 22 August and the last on 05 September. Because members of the reconnaissance team were delayed CRPM and CRPSSM decided to combine the reconnaissance phase with the set-up phase to make up for lost time. The full support team of eight travelled to Cape Roberts on 02-03 September.
5.5. Mainbody flights from NZ were also heavily disrupted. After a four-day delay the first and second flights made it on 03 and 04 October respectively before another period of delays. Local bad weather then delayed helicopter deployment to Cape Roberts, the first of the drillers not getting there till 07 October, four days behind schedule. A further six day bad-weather delay followed before key Cape Roberts-based scientists and science technicians arrived at Scott Base/McMurdo from NZ. By this time delays in getting some key items of drilling equipment (under-reamer and an electric motor) from NZ were threatening progress on sea riser deployment. Bad-weather and unservicability of aircraft caused delays of up to seven days to the planned drill schedule. However, in reality this was not as serious as it appeared because difficulties in deploying and embedding the sea riser and in establishing a regular coring routine added about six days to the schedule anyway.
5.6. The Crary Laboratory-based scientists and technicians were accommodated at Scott Base and McMurdo Station. Scott Base hosted 17*, made up of one Australian, four British, three Germans, and nine New Zealanders. Every Crary Laboratory-based scientist was encouraged to visit Cape Roberts and overnight so as to gain a fuller appreciation of the field operation. Most availed themselves of the overnight option. (*It should be noted that four of these individuals spent in excess of 10 days each at Cape Roberts.)
a. | Australia:
|
b. | Britain:
|
c. | Germany:
|
d. | Italy:
|
e. | New Zealand/USA:
page 5
|
With the exception of Leon Holloway all the CRP Visitors came to Cape Roberts in November. An ISC meeting was held at Cape Roberts 10-12 November 1998. Tom Maggs conducted an independent environmental assessment of the Project from 02-05 November 1998.
FIELD DEPLOYMENT AND FIELD EQUIPMENT
6.1. WINFLY Deployment August-September. CRPM was in regular contact with Winter-over Manager in the two months prior to WINFLY detailing the programme and support and resources required from Scott Base. CRP personnel were grateful for the use of the Scott Base garage and cold porch throughout the Winfly period. Scott Base personnel willingly assisted in the loading of sledges and containers. At Cape Roberts the first reconnaissance of the proposed CRP2 drill site was made on 07 September. The ice was 1.8m thick. Steady progress was made on erecting the CR Camp and the first hot showers were taken on the evening of 11 September and the Camp became fully habitable on the 13th.
6.2. Pyne, Howat and Conaglen returned to Scott Base in H1 on 15 September for five days to complete important engineering and scientific tasks before returning to Cape Roberts. Two sledges and two fully loaded containers (additions to the Mud Hut and Drill Site Lab) were loaded and hauled to Marble Point by the Americans on 26 September. They were met there by Pyne, Knox and Howat with the D6, who on-hauled the train to Cape Roberts the following day.
6.3. The normal sea ice route from Scott Base to Marble Point was blocked by a large active west-east crack that extended across McMurdo Sound from the Strand Moraines and finally swung north to near Tent Island where it petered out. The USAP sledge train had to head north almost to Tent Island before it could make westward progress. The route from Marble Point to Cape Roberts was reasonably straightforward but three cracks had to be bridged for safe travel by the D6. The preferred sea ice route to the Drill Site was to the north of Cape Roberts (5kms) before 'turning' the CR Crack and heading ESE. The route was 25kms long and passed through a couple of patches of rough ice which slowed progress (after a helicopter reconn in early October changes were made to the route to avoid the worst of the rough sections).
6.4. The support team at Cape Roberts spent the second half of September establishing the Drill Site camp. The two ice holes were drilled on 08 September to enable deployment of the under-ice flotation bags and then the start of the sea riser deployment.
6.5. Mainbody Deployment/Redeployment October-December. The first of the Mainbody crew - drillers and the remaining support staff - arrived at Scott Base on 03 October, and at Cape Roberts on 07 October, having done an Antarctic Field Training refresher course. Helicopter support remained 'patchy' for the next week or so, mainly due to unsettled weather. Regular shift change helicopter operations began on 16 October. The regular and smooth movement of personnel and cargo through Scott Base page 6 (and McMurdo) to Cape Roberts was the responsibility of the CRP Liaison Officer. His role was pivotal in the successful deployment and then ongoing movement of personnel and cargo between Christchurch, Scott Base/McMurdo and Cape Roberts.
6.6. Redeployment of personnel and science cargo to New Zealand went reasonably smoothly, in spite of an apparent lack of bed space at Scott Base and the threat of a lack of seats on aircraft returning to NZ, especially after the closure of the ice runway. Most of the drillers, the science technicians and some of the Cape Roberts-based scientists were able to return to Scott Base via a planned night-over at Vanda - a small reward for all their efforts.
6.7. Field Equipment. Relative to the size of the Project and the large number of personnel at Cape Roberts, only a small amount of field equipment was drawn from Scott Base stocks. In keeping with the Project's policy of 'self sufficiency' wherever possible, CRPM instituted CRP-owned light weight survival bags for people taking the shift change helicopters. Not only did these bags reduce weight and time for helicopter operations, they took considerable pressure off the limited supply of Scott Base survival bags. Scott Base-supplied field equipment was requisitioned in the normal manner and returned to store at the end of the season.
6.8. Scott Base Equipment. Throughout the drill season requests were made to Scott Base (and occasionally McMurdo) for the loan of specialist tools or the use of urgently required consumables such as plumbing and mechanical parts. These items were gratefully received and returned (and in some cases replaced) as soon as possible. The reality of the situation is that a Project the size of Cape Roberts, being conducted in a reasonably remote location, cannot hope to stock spares for every eventuality or have extensive repair facilities.
TRANSPORTATION
7.1. Christchurch-McMurdo Air Operations. The early part of the 1998/1999 season was disrupted by bad weather and CRP suffered delays in personnel and freight arrivals. Although frustrating and inconvenient at the time these early delays did not adversely affect the outcome of the drilling and science operation. At the end of the drill season there was concern expressed by Project management that unnecessary pressure was applied from Scott Base to finish early and have personnel 'off the Ice' before the ice runway closed. The threat of 'not getting home till after Christmas' was exaggerated and added to the already stressful task of making CRP2 a success. All Project personnel returned to NZ on or about the dates originally planned.
7.2. Cargo. Refer to CRP2 Cargo, Para 4 above, for cargo details. Overall the movement and delivery of cargo went well, especially so given the high amount air freighted (some 46,000 lbs ex Christchurch) and the often short notice to purchase and deliver. There is room for improvement in the way urgent cargo is tracked from NZ to Cape Roberts and better ways of doing this will be instituted for CRP3. CRPSSM was critical of the delay and damage done to science cargo that was returned to NZ after the drilling phase eneded. It seems the problem here is that when CRPLO departs Scott Base there is something of a vacuum created and 'loss of ownership' and CRP equipment can be overlooked. Hopefully CRP3 will plan for this.
page 77.3. Both German science groups (Niessen and Wonik) on the Project brought radioactive sources as part of their science cargo. Both scientists reported that this administratively sensitive cargo was moved smoothly through 'the system'. Niessen elected to leave his low grade source in storage at Cape Roberts until CRP3, thereby saving a good deal of paperwork.
7.4. Helicopter Operations. In CRP2 a total of 228.7 hours were flown of the 300 hours allocated. Of that, 217 hrs were flown in the drill operations phase, and the remainder in the January-February maintenance and winterisation phase. Refer to Appendix 1 for a breakdown of helicopter hours by week. The Project was well served by both the RNZAF and PHI. After some exuberant flying by RNZAF pilots on CRP1, the more measured approach by this season's RNZAF crews was appreciated by those who rode helicopters daily to work. CRPM was particularly appreciative of the effort by the RNZAF crews to back-load trash to Scott Base.
7.5. CRP Vehicle Fleet. The CRP2 vehicle fleet consisted of two Caterpillar bulldozers, -D5 and D6 models, a Kassbohrer PB 170 equipped with a Hiab crane, four Bombardier skidoos, a 4 × 4 Honda motorbike and two Haaglunds all-terrain vehicles. With the exception of the Haaglunds and the Honda motorbike all the other vehicles were wintered-over at Cape Roberts. The Honda motorbike arrived at Cape Roberts in late September on the sledge train to replace the unreliable ASV (all seasons vehicle) Track-Truck which was returned to Scott Base at the same time. Vehicle serviceability was generally good throughout the drill season. During the maintenance phase all vehicles were serviced. The skidoos are 'showing their age' and will require increased servicing to see out CRP3 and the clean-up year. A major job was undertaken at Cape Roberts in January when the right-side pivot shaft on the D6 was replaced. This involved the removal of the tracks, the blade and the track roller frame to access the worn shaft. It would not have been possible without the heavy lift capability of the Hiab crane on the Kassbohrer.
EVENT DIARY
8.1. Refer to Appendix 2 for an outline event diary and Appendix 3 for the CRPSSM's report covering drilling and science events and issues pertaining mainly to the Drill Site operation. The CRPM wrote daily situation reports (Sitreps) throughout the drill operation phase of CRP2. These recorded movement of personnel to and from Cape Roberts, daily weather, sea ice conditions, personnel welfare and drilling progress. The Sitreps are not reproduced in this report but can be accessed through Ant NZ records if required.
HEALTH AND SAFETY
9.1. No member of the CRP2 team suffered any serious illness or injury while in Antarctica. At Cape Roberts there were only minor injuries reported; eg. two strained backs, various muscle strains, a wrist injury and a welding burn. There were a couple of cases of cold/throat infections and a passing 24 hour-type flu, but fortunately that is where it ended.
9.2. Paramedic/Camp Manager Position. Colleen Clarke assumed the role of Paramedic/Camp Manager and immediately made her mark in both positions. First-aiders were identified and trained for emergencies at the Drill Site. First aid equipment page 8 was reorganised and new kits made up for each skidoo. Personnel feeling unwell or with a minor injury could approach Colleen with confidence. Colleen took an active role in the weekly staff safety meetings. She was also responsible for health and safety in the Camp, frequently making suggestions for improvements. And finally she tested the Camp's water supply daily for its pH level and weekly for bacteria count. The water was 'dosed' with sodium bicarbonate to maintain an optimal pH of between 7.8 and 8.2, as recommended by Ant NZ's water expert, Tim Donaldson of Ace Water Treatment Ltd. All bacteria counts were negative during the season. In mid-October a water sample was sent to Tim Donaldson in Christchurch for more specialised analysis of impurities such as copper and lead. Levels of these substances were either non-existent or well within acceptable levels.
9.3. A member of the Cape Roberts team who suffers from a potentially communicable disease was self administering injectable medication. Both CRPM and Paramedic were aware of this and suitable disposal arrangements for the used syringes were made. However, through an oversight the Scott Base medical office was not aware and became alarmed when used syringes were found in a rubbish bin at Scott Base. The individual concerned acknowledged a lack of forethought on his part but in his defence said there was no obvious 'sharps container' and he didn't know who to see about such a facility. This incident highlighted the need for better communication and access to medical files by all who should be 'in the loop' in such a case.
9.4. Safety Meetings. Weekly safety meetings were held throughout the drill operation phase. The pattern that worked best was the Drill Manager conducted a Drill Site meeting of all day shift personnel on a Friday. Notes from this meeting were given to the CRPM who then conducted a second meeting at CR Camp on the Saturday involving all night shift and support staff (not otherwise at the Drill Site meeting). Notes from both meetings were then posted on the noticeboard in the Warm Vestibule for everybody to read. Feedback from these meetings was positive, and the information useful. The key to the acceptance of the meeting format was the 'no blame' theme - people were there to learn, discuss and propose alternatives, and not to lay blame.
9.5. Incident Reports. CRPM filed three incident reports to Manager Scott Base during the drill season. All were classified 'near misses'.
a. | The first occurred when a pillion passenger on a skidoo fell off when the skidoo went over an obstacle. Speed nor carelessness were not at issue, except that the passenger wasn't holding on well enough. The real danger was a sled was being towed behind the skidoo and the passenger was lucky not to be struck or run over by it. Thereafter no passengers were to travel on skidoos towing a sled. |
b. | The chef was very lucky to escape serious fat burns when there was an 'explosion' of boiling fat from the CR Camp's deep fat fryer. This was caused by a build up of water in the fat from repeated cooking of water-logged parboiled potatoes. The chef should have recognised the danger.page 9 |
c. | A party was caught out on the Wilson Piedmont in a white-out when returning to CR Camp from a climb of Mt England. They were travelling with two skidoos and trailers and had all necessary survival gear. The leader of the group of five was an experienced climber and had three seasons Antarctic experience. He elected to push on, got off the route and didn't stop until the party had become thoroughly disorientated. Camp was made but not before they discovered they had ventured into a crevassed area. The weather lifted about three hours later and they safely returned to Camp. This incident raised a number of important issues regarding field safety and leadership. |
COMMUNICATIONS
10.1. Three communications facilities were available to CRP2. They were telephone links utilising 'Country' sets, HF radio and VHF radio. HF and VHF radio provided only voice communication, while the telephone system provided voice, data and facsimile transmission. There were three distinct communication phases during CRP2 - Winfly (September), drill operations (October-November), and close down/maintenance (December and January). The operational phase was the only one which had all communication facilities functioning. The total communications suit was only just adequate during the main operational-science phase of CRP2. At times, because of unserviceability, interference and overload the communication system was variously criticized as limited, cheap, ill-conceived, user-unfriendly and stress inducing.
10.2. HF radio, using 5400kHz, was only used on the Winfly traverses to and from Cape Roberts when the vehicles lost comms on VHF. Thereafter it was there as a radio of 'last resort' in an emergency.
10.3. VHF radio was the workhorse of the communications system, particularly between CR Camp and the Drill Site and between vehicles and the two camps and Scott Base. The majority of the VHF sets (some 15 including vehicle radios) were supplied from Scott Base stock. The base stations at both camp sites are CRP-owned. Performance during the Winfly period was excellent once the Piedmont VHF repeater (behind Cape Roberts) had been installed. However, it did deteriorate as the season progressed and at various times Channels 3 and 5 were being constantly interchanged in search of better performance.
10.4. The telephone system consisted of two lines - line 1 was set up once the Piedmont repeater was activated at Winfly and provided a reliable if static voice line to Scott Base and the world. The second line was transmitted through an intermediary repeater on Hoopers Shoulder, Mt Erebus. This could only be activated in early October once helicopter flying began. The quality of this line for most of the time was suitable for voice, data and facsimile transmission. It was, therefore, in high demand. Not only was the demand on it too much, data and facsimile transmission could easily and inadvertently be cut because of the way the system was configured at CR Camp.
10.5. As drilling progressed one of the most serious limitations of the communications system became increasingly apparent - there was no 'private' link, namely a telephone or scrambled radio link, between the Camp and the Drill Site. CRPSSM and the Drill Manager grew increasingly reluctant to discuss drilling issues and decisions on 'public' VHF radio and this adversely affected the working relationships in the on-site management team.
page 10- the system was conceived in 1994 with a negligible budget,
- in 1994 it was not appreciated how much all personnel on the Project would utililise phone, data and facsimile facilities if they were made available, and
- based on the mid-1980s CIROS experience nobody expected the drilling to be as difficult and demanding as it was on CRP1 and CRP2, necessitating good quality and private communications when frequent 'hard' and sometimes debatable decisions had to be made at short notice by the management team.
ENVIRONMENT REPORT
11.1. The CRP2 Environment Report is attached as Appendix 4. Note that this report is submitted to Ant NZ's Environmental Manager who in turn incorporates it in the annual environmental return to EARP. The Environment Report contains Appendices on person-days and visitors at Cape Roberts and a hazardous substances report.
Jim Cowie
Cape Roberts Project ManagerMay 1999
Appendices;
- CRP2 Helicopter Hours 1998/1999 Season.
- CRP2 Event Diary.
- CRP2 CRPSSM's Report dated Feb 99.
- CRP2 EOS Environment Report dated Feb 99.
CRP2 HELICOPTER HOURS 1998/1999 SEASON
Appendix 1 to CRP2 Log Report dated May 1999
To Week End | 10-Oct | 17-Oct | 24-Oct | 31-Oct | 7-Nov | 14-Nov | 21-Nov | 28-Nov | 5-Dec | 12-Dec | 16-Jan | 23-Jan | 30-Jan | TOTAL |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Projected | 35.0 | 35.0 | 25.0 | 25.0 | 25.0 | 25.0 | 30.0 | 30.0 | 30.0 | 30.0 | 5.0 | 2.5 | 2.5 | 300.0 |
Actual | 7.8 | 24.1 | 26.7 | 25.4 | 31.8 | 22.9 | 28.5 | 29.5 | 24.0 | 4.1 | 1.2 | 1 | 1.7 | 288.7 |
Difference | −27.2 | 10.9 | 1.7 | 0.4 | 6.8 | −2.1 | −1.5 | −0.5 | −6.0 | −25.9 | −3.8 | −1.5 | −0.8 | −71.3 |
Accum. Diff. | −27.2 | −38.1 | −36.4 | −36.0 | −29.2 | −31.3 | −32.8 | −33.3 | −39.3 | −65.2 | −69.0 | −70.5 | −71.3 | |
TOTAL | 7.8 | 31.9 | 56.6 | 84.0 | 115.8 | 138.7 | 167.2 | 196.7 | 220.7 | 224.8 | 226.0 | 227.0 | 228.7 |
CRP2 1998/1999 EVENT DIARY
Appendix 2 to CRP2 Log Report dated May 1999
DATE | EVENT |
---|---|
22-Aug | Howat, Ridgen, Sinclair arrive Scott Base (SB) ex Chch. Begin preparations for reconn. |
31-Aug | Clarke, Conaglen, Knox, Pyne, Reid arrive SB. |
1-Sep | Cowie arrives SB. |
2-Sep | Support team of eight depart SB in H1 and H2; overnight near Butter Point. |
3-Sep | Support team arrive Cape Roberts (CR) 1500 hrs. |
5-Sep | First containers/sledges hauled off CR. |
7-Sep | Conaglen, Pyne reconn drill site area - ice 1.8m thick; water depth 178m; DS at S77.006 E163.719. Temperature at SB reaches −50C. |
11-Sep | Utilities containers set up and first hot showers. |
13-Sep | CR Camp fully operational; Conaglen, Howat. Pyne depart CR for SB overnighting MPt. |
21-Sep | A heavy sledge route is finally determined SB to MPt via Tent Is. |
22-Sep | Conaglen, Howat, Pyne depart SB for CR overnighting at MPt. |
25-Sep | Conaglen resigns as Field Assistant/Carpenter. |
26-Sep | Americans depart SB for MPt hauling 4 CRP sledges (2 Challengers & Delta). Howat, Knox, Pyne depart CR for MPt in D6 and H2 with crack-bridging sledge (ASV on board) to rendezvous. Overnight MPt and return CR following day. Three cracks to bridge. |
29-Sep | First Mainbody flight cancelled. |
3-4 Oct | All 10 drillers, Holloway and remaining support staff (3) arrive SB ex Chch. |
5-Oct | Sea ice at Drill Site now 2m thick. |
7-8 Oct | CRPM, all drillers plus Holloway, two support staff, three divers (ex McM) arrive CR. Two 1m diameter holes drilled in sea ice and two air bags positioned in water under rig. Conaglen departs CR for SB and NZ. |
9-Sep | Sea riser deployment begins. |
14-Oct | Core technicians arrive and Sinclair (CRP Carpenter) departs CR for SB and NZ. |
15-0ct | Embedment of the sea riser into the sea floor begins. Brice arrives CR ex SB W/O to replace Conaglen as temporary Field Assistant. |
16-Oct | First core recovered. |
18-Oct | Cementing-in of sea riser a failure and repeated. All of CR 'permanent staff now in residence. |
20-Oct | Holloway departs CR for SB and NZ. Ackerly and Single (TVs Wild South programme) arrive to film Project. |
24-Oct | 50m bsf reached in CRP2 hole. James Barker USAP photographer arrives to photograph Project. |
25-Oct | While attempting to further embed the sea riser the under-reamer is temporarily 'lost' in the hole. |
26-28 Oct | Brice, Cowie, Howat, Knox depart CR for MPt fuel run, returning with 164 full drums. |
28-Oct | Sea riser further advanced to 12.2m bsf and again cemented-in. New hole now CRP2A |
30-Oct | 50m bsf reached in new CRP2A hole. Growing concern at high rate of mud fluid loss. New mud ordered, in all 2,625 kg (1,000 kg each of XCD Poly and PAC-R and 625 kg Guar Gum). |
31-Oct | Icetrek Expedition visits CR Camp and DS with TVNZ film crew. |
2-Nov | 100m bsf reached, core recovery rate improving and reduced loss of fluid. Independent environmental monitor, Tom Maggs, arrives with Ant NZ Enviromental Manager. |
3-Nov | 150m bsf reached. CRP DVs Carter and Fox arrive at CR with CEO Ant NZ. |
5-6 Nov | A successful 20 hour down-hole log conducted to depth of 172m bsf. |
6-Nov | Brice departs CR for SB and NZ. |
7-Nov | HQ coring stopped at 199m bsf and HQ rod cemented-in. |
10-Nov | 200m bsf reached. Coring recommenced using NQ rod. |
12-Nov | 250m bsf reached. |
13-Nov | Cita, Davey, Tessensohn, Thomson, Webb (all ISC members) and Fuetterer (OMG member) arrive. |
14-Nov | 300m bsf reached. Borg (NSF), Anderson and Huch, CRP visiting journalists arrived. |
16-Nov | 350m bsf reached. Cowie, Pyne depart CR for SB to attend combined ISC/OMG meeting. |
17-Nov | 400m bsf reached. |
18-20 Nov | Howat, Knox, Reid depart CR for second MPt fuel run; returning with 158 full drums. A fourth crack had to be bridged en route. |
20-Nov | 450m bsf reached. Horizontal drift of ice from over hole 9m - margin remains acceptable. |
21-Nov | 500m bsf reached. Italian TV film crew (3) arrive ex TNB for overnight filming. |
22-Nov | Hydraulic chuck replaced with mechanic chuck due to failed bearings. |
23-Nov | 550m bsf reached. Noticeable ice melt occurring at drill site and at CR transistion. |
24-Nov | 600m bsf reached. Decision taken to end coring 25 Nov to allow down-hole logging. |
25-Nov | Drilling stopped at 1420 hrs at depth of 624.15m bsf. Steve Brown, carpenter, arrives CR from SB. |
26-29 Nov | Down-hole log conducted to bottom of hole. Tool stuck in hole at 441 m bsf on 27th. Tool abandoned on 28th and final log done of upper hole. Party time at CR for 42 pers. |
30-Nov | HQ rod cut and recovered and CRP2 hole cemented. Scientists and drillers begin to depart CR, some via an overnight at Lake Vanda. |
1-2 Dec | Sea riser recovered. Outer casing successfully cut with CDC charge. Divers assisted. |
1-4 Dec | Drill Site decommissioned; all elements returned to CR, except one stuck under-ice 5t air bag.page 2 |
5-10 Dec | CR Camp decommissioned by team of 7 support staff. |
11-12 Dec | Support team return to SB in H1 and H2 overnighting MPt. |
13-Jan-99 | Howat, Reid, Ridgen arrive CR for maintenance/winterisation work. The 5t air bag, abandoned at DS in December is recovered. |
22-Jan | Cowie arrives CR. |
25-27 Jan | Ant NZ's Environmental Mngr at CR for monitoring work. Soil and water samples 'clean' of hydrocarbon contaminants. |
29-Jan | Maintenance team depart CR for SB and NZ. |
* Scientists and Science Technicians based at Cape Roberts.
** Scientists and Science Technicians who divided their time between Cape Roberts and Crary Laboratory, McMurdo Station.