Other formats

    Adobe Portable Document Format file (facsimile images)   TEI XML file   ePub eBook file  

Connect

    mail icontwitter iconBlogspot iconrss icon

Immediate report of Victoria University of Wellington Antarctic Expedition 1989-90: VUWAE 34

Field Transport

page 35

Field Transport

NZARP Vehicles
Hagglunds BV206 #H26

This vehicle is in a standard configuration with "trailer caboose" and is powered with a Ford petrol engine. The machine was allocated to K042 for our sea ice operation and glacier travel. A Maudheim sledge was lowed with up to 1800kg of cargo without difficulty up to Cape Roberts, partly unloaded then used within Granite Harbour. H26 generally performed very well without any significant mechanical problems. Ice studs had been fitted to the tracks prior to leaving Scott Base and these certainly improved vehicle traction on polished sea ice and on the 25 - 30° ice slope terminus of New Glacier.

Table 1. Vehicle diary Hagglunds BV206 #H26

It is not possible to accurately measure fuel usage in the field because we did not have a metering fuel pump and the vehicle tank gauges are not accurate. We used approximately 875 of Mogas and travelled 855 km giving an average fuel consumption of 1 litre/km which includes consumption while idling. A consumption rate of 1.25 litre/km should be a suitable figure to use for planning purposes.

This vehicle proved very suitable for general sea ice based work because it was reliable, comfortable, maneuverable and well controlled when crossing sea ice cracks. I would suggest however that some consideration be given to providing a choice of interchangeable modules for the rear caboose. For our sea ice operation a truck type flat deck with skies would be better to transport and operate some of our heavier equipment.

Our experience in extracting H26 from a crevasse has also indicated that rescue equipment should be carried and possibly some operating procedures reviewed. The electric winch on H26 was of little use when the vehicle is stuck and cant turn to level-wind. Consequently the wire cut itself during our first attempt to recover the vehicle. Chain hoists, TIRFOR hoists and a timber jack worked well during the vehicle recovery. It also became obvious that a Hagglunds te very vulnerable in a crevasse rescue situation if the hydraulic rams linking the front cab to the trailer are damaged either when falling into the crevasse or during the recovery operation. It is important therefore to move or lift the vehicle carefully so that the two parts of the vehicle remain in the correct relationship with each other. Any attempt to pull a Hagglunds out with another vehicle (such as a bulldozer) should therefore be considered very carefully to avoid over stressing the linkage system. Some consideration should also be given to page 36 rescuing the vehicle if it falls well below the crevasse lip. In this case some sort of lifting structure (e.g. like a davit) would need to be erected at the edge of the crevasse so that the vehicle could be lifted before being pulled out. Such a structure could be in a "bolt together" form that could be "footed" into the crevasse edge in a similar way to timber dead men. In our experience the survival box carried on the roof of the rear cab also caused difficulties because it was extra weight that was not required because we had our own camp equipment and also made the rear cab top heavy. Our camp equipment was carried in the rear cab which required careful unloading once in the crevasse. We may have been better off spreading our load onto a lowed sledge in this situation. It is also difficult to decide the best preparation for personnel travelling in the driving cab when travelling in areas of potential crevasses. The best compromise in this situation is to have all personnel wearing harnesses and have ropes available both inside and outside the cab to tie into.

Suggested list of extraction equipment, most field operations:
  • 2 × chain hoists (to lift vehicle)
  • 2 × TIRFOR hoists with wire cable
  • 4 deadmen (200 mm × 200 m × 1 m timbers)
  • Chainsaw (to place deadmen)
  • Chain slings
  • vehicle jacks (normally carried in vehicle tool box)
  • Deep field operations (in addition to the above)
  • Lifting frame (timber or steel pipe?) assembled at site to lift vehicle out of crevasse.

In a deep field situation it would be likely that at least two vehicles of similar capacities would be operating. Our crevasse experience does however highlight the problems of a single vehicle operation even though we were well served by helo from Scott Base.

Maudheim Sledge

This sledge was purchased with H26 and is larger than previous maulheim sledges used by NZARP. It is a good size and robust for our operation and has polyethylene shoed skies which makes towing easy although the sledge should only be used on snow or ice. We did note however that a lot of the timber sledge components where laminated and were delaminating in places. The sledge could also have rings fitted to make attaching cargo straps easier.

Helicopter Operations

The RNZAF Iroquois was used during H26 crevasse recovery to bring personnel from Scott Base and bridging timbers from Cape Roberts to the crevasse site. The crew's willingness to standby while the recovery was in progress was most appreciated but the weather conditions were deteriorating and I asked them to return to Marble Point and eventually McMurdo Station.

A Helo operation was scheduled to recover the mooring in Granite Harbour on 5 January. Equipment was underslung from Cape Roberts to the mooring site and later slung back to Scott Base. The operation went well but unfortunately the helo ran out of crew time because they took longer than expected to move the NZARP group in the Convoy Range so we couldn't do the planned aerial photography at Cuff Cape. Pat Sole (K191) however completed this photography later in January. It was also unfortunate that we couldn't programme to stay overnight at Cape Roberts to complete the met. instrument checking because of a high helo use the following day. In general the operation went well and we are grateful to the Scott Base Operations Manager for his programming.

Event Diary
3 Nov Chch - McMurdo flight delayed. Received K042 event Directive in Chch after request to Ant. Div.
4 Nov To Scott Base. Pyne, Goodwin, Möller.page 37
5 Nov Prepared field camp equipment.
6 Nov Sea ice / Hagglund shakedown cancelled due to bad weather.
7 Nov Storm all day - preparations at Scott Base.
8 Nov Goodwin, Möller, Rodgers on glacier travel survival course.
9 Nov Sea ice course to Turtle Rock. K042 and K191 personnel plus G. Kennedy (survival school instructor), and A. Belcher (Radio Operator). Weather deteriorated in the evening - cancelled move to Butter Point.
10 Nov Poor weather - moved sledge 12 km from McMurdo, returned to Scott Base.
11 Nov Storm @ Scott Base - no movement.
12 Nov Left SB for Cape Roberts. Straight line route McMurdo to Marble Point on good first year ice. Refuel @ south side Marble Point 1987 MOGAS. Good travel onwards to Cape Roberts - Total trip time 11 hours. Checked tide gauge and found pressure transducer missing.
13 Nov Prepared mooring equipment, down loaded tide gauge data-lost transducer readings 6 February 1989.
14 Nov Bathymetry in Avalanche Bay for mooring site. Checked terminus of New Glacier for suitable Hagglund (H26) route. All first year ice enroute to New Glacier except 2 km off New Glacier.
15 Nov Helo aerial photography with K191; C.Roberts, ML England, ML Marshall and north peak of Mt Suess where mast/caim were established. K042 return to C.Roberts. K191 to Vanda.
16 Nov Set mooring with current meter and 7 small sediment traps in "Avalanche Bay channel site".
17 Nov Began establishing 4 m met. mast addition to the tide gauge recording equipment at C.Roberts.
18 Nov Completed met. mast installation. Poor weather in early evening.
19 Nov Tested vibro-corer pressure housings to 850 m depth at S-216 site in outer Granite Harbour. Travelled to New Glacier and upwards heading for the Flatiron. H26 fell in crevasse above the crevasse field on the top north side of New Glacier. Extension of the crevasse field not evident on aerial photographs and obscured by 1 m thick snow and wind slab. See accidents section for further details.
20 Nov Recovery of H26 with assistance from Scott Base personnel and Kiwi helo.
21 Nov Scott Base personnel return to SB. Return via New Glacier to Granite Harbour. Recon. of New Glacier moraine below Mt. England, Devils punch bowl, Finger Point and Cuff Cape. Camped with S-216 at NE snout of MacKay Glacier Tongue (MGT)
22 Nov D. Hotop and P. Sole to K042 from Scott Base. Goodwin and Rodgers return to Scott Base. Goodwin return to New Zealand. Recon. of north armpit of MGT and Point Retreat and return to Cape Roberts.
23 Nov Work at Cuff Cape and bathymetry completed at Avalanche Bay. Return to Cape Roberts in evening.
24 Nov Work at Cuff Cape and recover/redeploy the mooring. Weather deteriorated in late afternoon.page 38
25 Nov Work at Cuff Cape survey moraine ridge system related to small hanging glacier.
26 Nov Prepared mooring equipment for January recovery. Packed equipment for return by sledge to Scott Base. Checked met. mast operation and down loaded data.
27 Nov To the Flatiron. Recon. of ponds on the Flatiron and beach ridges at C.Geology and Botany Bay.
28 Nov Left C. Roberts and return to Scott Base. Picked up 44 gal. MOGAS at Butter Pt., tide crack too wide to cross, returned fuel to Scott Base.
29 Nov Equipment return and cleanup. Packed cargo for return to New Zealand.
30 Nov Möller to lower Taylor Valley with K042. Pyne-Boomerang flight, McMurdo-McMurdo.
1 Dec Pyne return Chch.
4 Dec Möller to Scott Base from Taylor Valley.
5/6 Dec 1990 Möller return to New Zealand.
4 Jan Pyne to Scott Base.
5 Jan Pyne, Hotop, Kernot to Granite Harbour. Pick up equipment at C. Roberts. Recover mooring after initial recovery problem. Return to C. Roberts, download current meter data and attempted maintenance of met. mast. Computer problem - left met. mast non operational through winter 1990. Could not do Cuff Cape Aerial photography because of helo crew time overrun.
6 Jan Packed equipment for return to New Zealand. Checked WINKIE drill bits at Scott Base. Pyne transferred to McMurdo to join S-216 for preparation on Ross Sea 90 Cruise.
7-10 Jan Preparation of equipment at McMurdo with S-216. Transferred to USCGC Polar Star in early evening at McMurdo for rendezvous with MV Polar Duke on 11 Jan.
11 Jan-9 Feb Ross Sea 90.
9 Feb-14 Feb Return equipment etc for winter storage at McMurdo.
14 Feb Pyne return to Chch.