Estimate
.gif)
Estimate.
The estimated cost of constructing and equipping the proposed tramways may be approximated as follows:—
1st. Section. Laying down endless wire rope between City terminus and top of Leven street, Roslyn, including all permanent way with stationary engines and cars necessary for present traffic | £15,000 |
2nd. Section. Approximate cost for laying down the permanent way, say 3 miles, at £1,500 per mile | £4,500 |
Road improvements | 800 |
Equipments including locomotive or horses and cars | 3,000 |
£8,300 | |
Total cost of scheme— | |
1st. Section | £15,000 |
2nd. Section | 8,300 |
£23,300 |
The above estimates do not include any compensation that may be required by the City or any of the municipalities.